Research on Grouting Technology with Abandoned Drilling Mud

More Information
  • Available Online: April 02, 2023
  • Published Date: January 24, 2011
  • In order to release the problems of the abandoned drilling mud discharging and treatment, the paper had a study on the preparation of the surface pre-gr outing grout with the abandoned drilling mud.With the sticky reduction and modification treatment of the prepared mud, the density and sticky of the grout would be redu ced.The plasticity strength of the grout would be slowly increased and could be reached to 50 kPa after about 15 h.The grouting project with S boreholes for the mine m ain shaft of Yuandian No.2 Mine, Huaibei Coal Mining Group had consumed the drilling mud grout of 7 606 m3.After the mine shaft excavation and measurement, the re sidual water inrush quantity at the grouting section of the mine shaft was about 3 m3/h and the grouting effect was excellent.
  • Related Articles

    [1]ZHAI Xiaorong, WU Jiwen, HU Ru, BI Yaoshan, LIU Wei, LI Ning. Study on surface pre-grouting reinforcement layer of stratified regenerated roof under bifurcated coal seam[J]. COAL SCIENCE AND TECHNOLOGY, 2022, 50(11): 30-39.
    [2]YUAN Dongfeng, GAO Xiaogeng. Study on curtain grouting parameters of vertical shaft in Dengying formation of southern Guizhou with thick aquifer[J]. COAL SCIENCE AND TECHNOLOGY, 2021, 49(3): 71-77. DOI: 10.13199/j.cnki.cst.2021.03.008
    [3]FENG Xu-hai. Modification Study on High Pressure Surface Pre- Grouting Reinforced Cement Base Material for Deep Mine Shaft[J]. COAL SCIENCE AND TECHNOLOGY, 2014, (9).
    [4]Study on Construction Technology of Surface Ground Pre-Grouting for Mine Shafts in Northwest China Mining Area[J]. COAL SCIENCE AND TECHNOLOGY, 2013, (2).
    [5]Study on Performances of Modified Urea Formaldehyde Resin Grout for Surface Pre-Grouting[J]. COAL SCIENCE AND TECHNOLOGY, 2011, (12).
    [6]Dilling-Grouting Simultaneous Operation Technology in Mine Shaft Construction[J]. COAL SCIENCE AND TECHNOLOGY, 2011, (1).

Catalog

    Article views (565) PDF downloads (0) Cited by()
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return