Advance Search
ZHANG Yongjiang LU Zhanjin, . Development and application of complete set of anti-reflection equipment for ultra-high pressure hydraulic seam cutting[J]. COAL SCIENCE AND TECHNOLOGY, 2020, 48(10).
Citation: ZHANG Yongjiang LU Zhanjin, . Development and application of complete set of anti-reflection equipment for ultra-high pressure hydraulic seam cutting[J]. COAL SCIENCE AND TECHNOLOGY, 2020, 48(10).

Development and application of complete set of anti-reflection equipment for ultra-high pressure hydraulic seam cutting

More Information
  • Available Online: April 02, 2023
  • Published Date: October 24, 2020
  • The existing slotting( reaming) device has low cutting efficiency for medium hard or hard coal seam,and there are relatively few supporting safety protect ion measures,which can not realize the remote operation of slotting. In order to solve the problem of safe and efficient seam penetration enhancement in medium hard 0 r hard coal seam,it is necessary to develop a complete set of slotting device with higher pressure.On the basis of comprehensive consideration of equipment efficiency, slotting depth and required flow rate of slotting slag,a high-pressure clean water pump was developed; by analyzing the distribution law of borehole flow field,and accor ding to the theory of water jet,a high-low pressure conversion slot cutter was developed; Based on the drilling slag discharge principle,the overall processing technology was adopted to develop the shallow spiral integral drill pipe; based on the narrow slot viscous fluid flow theory,the ultra-high pressure rotating water tail was developed using the gap seal design; based on the variability of underground coal mine roadway conditions,and according to the rated pressure and rated flow of high-pressure c| ear water pump,the design requirements of the overflow valve were determined,and the high-pressure remote control was developed; the pressure resistance and resist ance loss along the long-distance slotting operation were comprehensively analyzed,and the ultra-high pressure hydraulic hose was developed. Through the developme nt of key components,the ZGF-10( A) ultra-high pressure hydraulic slotting device has been successfully developed. The complete set of equipment has a working pre ssure of 100 MPa and it has the integrated function of dilling and cutting,which can realize remote control of more than 100 m.The safety protection device has formed a safety protection system for ultra-high pressure hydraulic transmission. At the same time, safety tests have been carried out on 8 items including no-load operation,wo rking pressure,working flow,sealing performance and pressure resistance of the complete set of equipment,and the contents of the tests were in line with the state relat ed testing requirements. The field application results show that: the ultra-high pressure hydraulic slotting device is used to relieve pressure and increase permeability of coal seam. The average single cutting coal output of through seam drilling is 0.85 t,and the cutting radius is 1.78 ~ 2.18 m,which can increase the pure amount of gas drainage by more than 2.0 times and shorten the time of reaching the standard by more than50%; under the condition of 47% reduction in the drilling volume of the bed ding drilling,the pure amount of single hole gas drainage can be increased by2.0 ~ 2.5 times ,and the cycle construction period of driving can be shortened by more tha n 60%.It shows that this method has high fficiency in seam cutting,and has significant anti-reflection effect in seam pressure relief after seam cutting
  • Related Articles

    [1]MA Li, SHI Xinli, LI Shugang, LIN Haifei, SONG Shuang, DAI Xinguan. Research on intelligent control model of gas drainage based on model predictive control[J]. COAL SCIENCE AND TECHNOLOGY, 2022, 50(8): 82-90.
    [2]WANG Liang, LIAO Xiaoxue, CHU Peng, ZHANG Xiaolei, LIU Qingquan. Study on mechanism of permeability improvement for gas drainage by cross-seam cavitation borehole[J]. COAL SCIENCE AND TECHNOLOGY, 2021, 49(5): 75-82.
    [3]YAN Baoyong CAO Liu ZHANG Jiagui, . Exploration on gas drainage technology and equipment of fracture zone in coal seam roof[J]. COAL SCIENCE AND TECHNOLOGY, 2020, 48(10).
    [4]TANG Enxian, DANG Lipeng, YAN Guofeng. Practices on precision gas pre-drainage based on time-space attribute in Huangling Mining Area[J]. COAL SCIENCE AND TECHNOLOGY, 2018, (8).
    [5]WANG Feng TAO Yunqi LIU Dong, . Study on pressure released scope of hydraulic flushing and gas drainage law[J]. COAL SCIENCE AND TECHNOLOGY, 2017, (10).
    [6]Li Jie. Gas Control Effect and Determination on Drainage Location of Directional High Level Long Borehole[J]. COAL SCIENCE AND TECHNOLOGY, 2014, (12).
    [7]SU Xian-bo LIU Xiao MA Bao-an PEI Gang FENG Wen-jun, . Repairing and Enhancing Permeability Technology and Equipment of Gas Drainage Borehole[J]. COAL SCIENCE AND TECHNOLOGY, 2014, (6).
    [8]FAN Fu-heng ZHANG Fu-wang QIN Ru-xiang, . Study on New Borehole Sealing Device of Gas Drainage Borehole Along Seam[J]. COAL SCIENCE AND TECHNOLOGY, 2013, (10).
    [9]Practice on Comprehensive Gas Drainage Technology in High Gassy Mine[J]. COAL SCIENCE AND TECHNOLOGY, 2012, (12).
    [10]Study on Numerical Simulation of Regional Gas Drainage in Outburst Seam[J]. COAL SCIENCE AND TECHNOLOGY, 2012, (11).

Catalog

    Article views (381) PDF downloads (532) Cited by()
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return