高级检索

工作面回采与支架回撤协同作业新技术

王志强, 王树帅, 苏泽华

王志强, 王树帅, 苏泽华. 工作面回采与支架回撤协同作业新技术[J]. 煤炭科学技术, 2021, 49(2): 21-29. DOI: 10.13199/j.cnki.cst.2021.02.003
引用本文: 王志强, 王树帅, 苏泽华. 工作面回采与支架回撤协同作业新技术[J]. 煤炭科学技术, 2021, 49(2): 21-29. DOI: 10.13199/j.cnki.cst.2021.02.003
WANG Zhiqiang, WANG Shushuai, SU Zehua. New technology of collaborative work between face mining and bracket withdrawal[J]. COAL SCIENCE AND TECHNOLOGY, 2021, 49(2): 21-29. DOI: 10.13199/j.cnki.cst.2021.02.003
Citation: WANG Zhiqiang, WANG Shushuai, SU Zehua. New technology of collaborative work between face mining and bracket withdrawal[J]. COAL SCIENCE AND TECHNOLOGY, 2021, 49(2): 21-29. DOI: 10.13199/j.cnki.cst.2021.02.003

工作面回采与支架回撤协同作业新技术

New technology of collaborative work between face mining and bracket withdrawal

  • 摘要: 基于现有采区最后1个走向工作面与煤柱采出工作面开采衔接时间长、工艺复杂、煤炭采出率低以及支架回撤巷道掘进工程量大等问题,结合梧桐庄矿2号煤层三采区182312(简称312)走向工作面及182312外(简称312外)煤柱采出工作面地质生产情况,采用理论分析、工业性试验等研究方法,提出了工作面回采与支架回撤协同作业新技术:在312工作面回采过程中完成312外工作面生产系统,312工作面贯通三采右翼出煤巷,利用支架对出煤巷进行留巷,在312外工作面推至支架留巷段,边推进工作面边回撤支架。研究表明:由极限平衡区公式计算得支承应力峰值叠加区宽度为7.2 m,在压力拱载荷作用下,由不同支架控顶距计算得煤柱宽度为6.6~7.7 m,最终确定了贯通前让压煤柱宽度为8 m;分析了312工作面在贯通出煤巷前基本顶不同断裂形式及其让压调节机理,计算分析得基本顶预断裂位置超前合理断裂位置1.4 m,因此采用支架高阻力停采等压16 h;在312工作面距出煤巷50 m前完成了巷内补强支护;312工作面距终采线14 m进行挂绳铺网,并在距终采线2.4~13.0 m铺设风筒布;312工作面贯通出煤巷后,制定了支架留巷工艺;支架留巷完成后,开始回采312外工作面,在312外工作面推至支架留巷段,采用“掩护式迈步台阶支架拆除法”边推进工作面边回撤支架。此技术实现了出煤巷的“一巷三用”,提高了煤炭回收率,简化了工作面衔接及支架回撤工艺,节省了巷道工程量及支护费用,最终实现了工作面回采与支架回撤的协同作业。
    Abstract: Based on the problems that long times mining connection, complicated process, low coal recovery rate between the last longwall working face and the coal pillar recovery working face of the existing mining area, and large amount of engineering in support withdrawal, combined with the geological and production conditions of No.182312 (abbreviated as No.312) longwall working face and No.182312 outer (referred to as No.312 outer)coal pillar recovery working face in the third mining area of No.2 coal seam in Wutongzhuang Coal Mine, theoretical analysis and industrial test and other research methods was used, the new technology of collaborative work between face mining and bracket withdrawal was put forward:the No.312 outer working surface production system was completed during the No.312 working face recovery process, the No.312 working face passed through the uphill without coal pillars and uphill was retained with support.When the No.312 outer working face was pushed on to the gob-side entry retaining section, the bracket was retracted while pushing the No.312 outer working face.The results have showed:abutment pressure peak superposition area was calculated 7.2 m by limit equilibrium zone formula; the width of the coal pillar is calculated 6.6~7.7 m from different bracket roof-control area under the pressure arch load; it was finally determined that the coal pillar was 8 m before the No.312 working face passed through uphill.Analyzed different fracture modes of basic top and their pressure regulation mechanism, calculated and analyzed that the basic top pre-fracture position was advanced the reasonable fracture position 1.4 m, therefore, stopped mining for 16 h and the bracket was with high resistance.Reinforcement support measures in the uphill was completed before the No.312 working face was 50 m away from uphill; started lanyard and paving when No.312 working face was 14 m away from stopping line; and the air duct cloth was laying within the range of 13~2.4 m from the stopping line; the process of gob-side entry retaining with bracket was formulated after the No.312 working face passed through the uphill.Began recovering the coal pillars after the completion of gob-side entry retaining; when the No.312 outer working face was pushed to the gob-side entry retaining section, the bracket was retracted while pushing the No.312 outer working face with the method of shielding type stepping bracket withdrawal.This technology realized that the uphill has three functions.The coal recovery rate and work efficiency have been improved, the process of working face connection and bracket retraction have been simplified, the amount of roadway engineering and maintenance costs have been saved.Finally, the collaborative work of working face recovery and bracket withdrawal was realized.
  •   182312工作面布置

      工作面协同开采布置示意

      312工作面支架留巷段

      支架沿空留巷示意

      喷浆及打设单体支柱施工现场

      支架回撤工艺示意

      工作面末采及支架回撤示意

      煤柱上方应力分布

      工作面前方支承应力分布

      留设煤柱两侧冒落拱示意

      基本顶断裂位置

      基本支护断面示意

      巷内补强支护平面

      挂绳上网配合风筒布施工

  • 期刊类型引用(17)

    1. 赵少凡. 煤矿井下综采面回撤通道安全支护技术的优化分析. 煤矿现代化. 2025(04): 88-92+97 . 百度学术
    2. 牛佳波,杨文岗,宋阿林. 围岩稳定性数值模型在支护方案优选中的应用. 内蒙古石油化工. 2025(04): 16-20 . 百度学术
    3. 张军,朱友恒. 综采工作面末采期间让压间隔煤柱宽度研究. 煤炭科技. 2024(02): 27-31 . 百度学术
    4. 胡成军,李杰,张坤,潘格格,马健,郭刚,毕经龙,杜明超. 基于掘锚一体机的快速自动铺网技术研究. 煤炭科学技术. 2024(09): 103-111 . 本站查看
    5. 欧阳振华,许乾海,张宁博,张天姿,易海洋,史庆稳,李文帅,王佳嘉. 井工煤矿全生命周期冲击地压防治体系研究. 矿业科学学报. 2024(06): 932-942 . 百度学术
    6. 刘怡. 基于综采面液压支架安全回撤技术的研究. 机械管理开发. 2023(01): 260-261+264 . 百度学术
    7. 乔建永,王志强,李廷照. 矿压峰值点极限和无煤柱末采技术研究. 中南大学学报(自然科学版). 2023(03): 880-894 . 百度学术
    8. 樊胜杰. 综采工作面支架高效快速回撤方法优化及应用. 江西煤炭科技. 2023(02): 65-68 . 百度学术
    9. 史佳斌,刘虎生,崔东亮,姬智,段伟. 回撤通道覆岩破断特征及巷道围岩稳定性研究. 煤炭工程. 2023(S1): 43-48 . 百度学术
    10. 张锐. 综采工作面液压支架快速回撤工艺应用. 机械管理开发. 2022(04): 177-178 . 百度学术
    11. 胡滨,王志超,张晓. 混凝土支柱与锚杆(索)联合支护系统应用研究. 煤炭科学技术. 2022(04): 91-98 . 本站查看
    12. 彭林军,岳宁,安亮,李申龙,蔡逢华,冯振华,李明辉. 超大采高综采工作面回撤通道支护技术研究. 煤炭科学技术. 2022(06): 204-210 . 本站查看
    13. 娄杰,徐严军,柏建彪,张栋,李斌,卞卡,刘峰. 叠加扰动下剩余煤柱应力演化特征分析. 煤炭工程. 2022(08): 84-90 . 百度学术
    14. 王志强,田野,王树帅,牟皓奇,刘吟苍. 基于基本顶断裂位置分析剩余煤柱稳定性. 中国安全生产科学技术. 2022(08): 51-58 . 百度学术
    15. 郑铁华,李金刚. 补连塔煤矿浅埋近距离煤层过上覆煤柱强矿压灾害防治机理及应用. 煤炭科学技术. 2022(S1): 71-80 . 本站查看
    16. 霍建军,杨景惠,孙波. 综采辅巷多通道回撤工艺通风系统管理研究. 煤炭科学技术. 2022(S1): 142-146 . 本站查看
    17. 冀永林. 综采工作面液压支架安全快速回撤工艺应用. 机械管理开发. 2021(12): 203-204 . 百度学术

    其他类型引用(2)

图(14)
计量
  • 文章访问数:  398
  • HTML全文浏览量:  9
  • PDF下载量:  537
  • 被引次数: 19
出版历程
  • 网络出版日期:  2023-04-02
  • 发布日期:  2021-02-24

目录

    SU Zehua

    1. On this Site
    2. On Google Scholar
    3. On PubMed

    /

    返回文章
    返回